Skip to main content
Planview Customer Success Center

Why do all the tasks have a number in the time sheet?

Question
Why do all the tasks have a number in the time sheet?

 

Answer
WBS numbering was enabled for the timesheet tasks

On the timesheet, go to Options and ensure to uncheck WBS Number.