Is it possible to total the real resources in RMW without including the generic resources? (2012 SP1)
Project Worksheet (PW) and Resource Management Worksheet (RMW) referenced in this article are based on Silverlight technology and are no longer available as of Changepoint 2020
Question:
Is there a way to total the real resources and not include my generic resource in Resource Management Worksheet?
Answer:
It is possible to total real resources and eliminate generic users by creating a view that groups by "Resource license type" and adding a "sum" calculation to demand effort. That would show a section for "Changepoint user" (real resources) and a section for generic resources. You can also filter on "Resource license type" and only display "Changepoint user".