Why does a resource appear only in the histogram and not the Gantt chart in the Resource Demand Scenario view, when viewing the report by function
The function in the Gantt chart comes from the demand item, not from the resource that is assigned to the demand item.
For example, if a task assignment is assigned to Joe, whose primary function is ‘senior analyst’ and the function selected on that task assignment is ‘project manager’, what is shown for the demand section is ‘project manager’. The histogram section would show ‘senior analyst’.