How is the PPC calculated for open tasks linked to a FF ?

Question
I have Open tasks linked to Fixed Fee.
For Open task, there are Planned Hours at task level and Planned Hours at task assignment level.
How is the Revenue Recognition PPC calculated ?


Answer
RevRec PPC uses the Total Planned Hours of the Open Task, but not the total of Task Assignment Planned Hours.

Additional Notes
About Assignment planned hours field =
Specifies the planned hours for all task assignments for an open task, if resource leveling is not enabled. If resource leveling is enabled, then all task assignments have 0 planned hours of hours.