QUESTION

In Scenario Comparisons, we see the numbers for opportunities (effort, cost, ...) being multiplied by the probability. Can this be avoided so that always the full amounts are being displayed?

 


RESOLUTION

This is an option that can be configured in System Management - Finance - Funding and Scenario setup.

Here you can choose for opportunities to show the full amounts or the amounts multiplied by the probability. In case this setting has changed, the effect will only be seen on the next day, as a job has to run at night that will update the numbers.