Question

When project is copied from a template, "Allow override of work location" is setup on the project and task/task assignment but it is not working in the time sheet.

If the users are manually added to the task, then the setup is working


Answer

The option "Copy select work locations and work codes from the source tasks and task assignments" was not selected on the Copy Project dialog. If the user does not select this option then both the "Allow work location override" and "Allow work code override" will be initialized to false and not updated. The metadata will be enforced if the task assignment is manually updated.

This is documented in the online-help. Project Management > Managing Projects > About copying projects > About completing the Copy Project dialog box at the bottom of the page.