Resource has two different Billing Rates

SYMPTOMS
We have a resource that has two different billing rates. One rate shows as $210 in a project. In another project, the same resource has a rate of $225.

REASON
The Billing Rate is based on the “effective date.” You can also specify which rate you would like to use by making a rate active or inactive. So it is completely normal that for different points in time different rates are active for the same resource.