I have a project set with Fiscal Period and I work with BAW.
I created an expense in BAW with a quantity and unit cost. However, I modified the extended cost in the BAW table for a fiscal period, but the unit cost and quantity are not updated.



As a best practice, use the field quantity and unit cost, and use the recalculate function available when right clicking on the table.
There's no reverse calculation that update unit cost and quantity from extended cost value.