QUESTION

How to enable or disable project level resource requests (project team)?

 


ANSWER

To enable resource requests on project level, you need to edit the engagement and open the projected resources tab. There, you find a check box to enable resource requests on project level. You need to be resource manager for the engagement staffing workgroup in order to be able to change this setting.