QUESTION:
We have a billable task with a billable billing role on the project worksheet. The billing role is on the engagement with the correct hourly rate. However, when we pull a report, the task is appearing as "Billable No."
ANSWER:
The time records included on the report were entered today.
There is an overnight job (Update Time Rate) that needs to run which will update time records to billable and set proper billing and cost rates. If you run the same report tomorrow this data will be correct.