Skip to main content
Planview Customer Success Center

Changepoint 2022-R6 Release Notes (22.00.048.000)

For information about accessing this release package see How to access Changepoint releases and patches.

Release date

July 29, 2022

Fixed issues

Product area

Request number

Description

APIs

CPC-2022-00371

System error -1 occurs when the API is used to submit time over 31 days.

Contracts

CPC-2022-00422

Incorrect function-billing role association is used for projected resources for contracts.

General Usability

CPC-2022-00433

Pressing the Tab keyboard key does not move the cursor through all columns in the contract billing rates row.

MSP Interface

CPC-2022-00423

Planned effort for task assignments is not validated against the maximum effort allowed for the project team when saving from Microsoft Project to Changepoint.

Outlook/Exchange Server synchronization

CPC-2022-00429

Cannot update or delete recurring calendar entries in Changepoint when synchronization direction is from Changepoint to Exchange server only.

Portfolio Planning

CPE-2022-00208

Project planned cost value does not render on portfolios for projects that have "Roll up planned information from subprojects to parent task" selected.

Project Management

CPC-2022-00224

When a project is copied and a default resource is selected, the planned effort for a deleted task assignment in the source project is copied to the target project.

Project Worksheet

CPC-2022-00103

Validation of maximum daily effort is not applied consistently on Project Worksheet.

Project Worksheet

CPC-2022-00185

Dragging the effort bar in Gantt chart sets forecast finish to 1 day later than planned finish in Project Worksheet

Project Worksheet

CPC-2022-00421

Unlocking a task also unlocks unrelated tasks.

Project Worksheet

CPC-2022-00425

Resources that are not contract projected resources or exempt resources are incorrectly available in Project Worksheet.

Project Worksheet

CPC-2022-00426

Resource Search dialog does not load properly when the task or task assignment duration is 0 and the browser language is set to a language other than English.

Project Worksheet

CPC-2022-00437

Total Planned FTEs for task assignments does not match the daily FTEs when there are no working days between planned start and finish dates.