Skip to main content
Planview Customer Success Center

Why are the time approver fields not available in the Edit Project dialog, even though they are enabled in Metadata?

The metadata setting only controls whether the field is hidden or displayed in the user interface. The setting does not control whether the field can be edited. 

The time approver fields in the Edit Project dialog box are available only when the option that allows project managers to specify time approvers is selected on the related engagement.