Task planned hours is set to 0

We have tasks with loading method "1 - Auto-distribute – update past and future". At one point we noticed that remaining planned hours have been set to 0. What is the reason?


The tasks in question reached their planned finish date. With the loading method "1 - Auto-distribute – update past and future", remaining planned hours are distributed into the remaining fiscal period. If the task has ended, however, there are no remaining fiscal periods therefore no more hours can be planned.