SYMPTOMS

A resource in a workgroup that prevents overbooking is planned in the project worksheet. Effort is changed in the current month, and despite there is no overbooking this month, there is an error message about overbooking.


ANSWER

Overbooking is checked for the entire duration of the task assignment, not only the current month or the section currently visible in the project worksheet. Please scroll through the entire duration of the assignment and check for overbooking. Also check the resources calendar for non-working days (e.g. vacation) or effort planned on other tasks or projects.