Using the GUI, dates till end of 2099 can be entered.

Using the API, dates till 12/31/9999 are accepted. This is the highest date possible in SQL Server. It may however cause issues in certain areas (like MSP interface) or can create performance problems.

If you insist on using 9999 as end date, use 12/30/9999 as end date and not the 31st; otherwise the calendar or resource demand analysis may error out.