Skip to main content
Planview Customer Success Center

Why the drop down list is missing when trying to create a task assignment in the Project Worksheet?

Question
Why the drop down list is missing when trying to create a task assignment in the Project Worksheet?

 

Answer:
Possible causes can be:

  • Resource requests are enabled
  • Preferred resources haven't been defined
  • Project level setting "Time-based project" is enabled which implies using the Service Scheduler (from Changepoint 2020, 19.00)