SYMPTOMS

A task assignment that has a manual allocation lost this manual allocation after a non-working day was added for the assigned resource.


ANSWER

This is the normal behaviour of Changepoint up to V2014 included. As effort cannot be allocated on non-working days, task assignments are redistributed evenly when a non-working day is added during the assignment duration.

Starting with Changepoint V2017 effort can be allocated on non-working days, thus there is no more need to replan existing task assignments.