Is it possible to create task dependencies (link tasks) between different projects?

You can create dependencies between tasks that are in different projects from the task profile page only.

You access the task from the Projects tree view or by searching and then click Actions > Create Task Dependency.

In the Create Task Dependency dialog box you can select predecessor and successor tasks from different projects.