MSP link changes the loading method in the project worksheet

QUESTION
When linking a project to MSP the loading method for task assignments is changed. We set all loadings methods to 0- Manually distribute - Update past only. But When a project is linked to MSP, the loading methods are changed to 3 - Manually distribute - No update. This is not the loading method used.


ANSWER
This is working as designed.
Whenever the project is linked to MSP, the loading method is changed to 3 as no changes to planned effort can be made in Changepoint. Thus, the loading method is set to 3 manual updates, to prevent any changes from happening.