Assigning a specific corporate calendar to a set of resources not in the same workgroup
QUESTION:
We need to assign a specific corporate vacation calendar to a set of resources that are not all in the same workgroup. Is there a way to assign a set of non-working days across a set of resources for this?
ANSWER:
Use individual calendar entries marked as non-working days. However, there is no way to assign non-working days across resources, unless it is by workgroup.