What are the criteria for a task assignment to be due for statusing in task status compliance report?

QUESTION:
What are the criteria for a task assignment to be due for statusing, e.g. via the task status compliance report?


ANSWER:

1. The project is active and of type 'Status required'.
2. The task status is not 'complete' and the flag 'Status not required' is not checked.
3. Task and assignment are not locked
4. The date of the previous status update is less than the next status due date. The due date is computed from the project record, using the fields 'First status' and 'Status every X weeks'.