Unable to assign a resource to a task, even though the Preferred Resource list is populated.

Resource requests and restrictions was set at system manager level, steps:

 1. Log into Administration section
2. Browse to Financial Management
3. Open Cost Structures
4. Pull up the specific Cost Structure
5. Go to Settings
6. Ensure that the "Enable resource requests and restrictions for all Initiatives under this cost structure" is unchecked.