Task assignments are not shown in the resource management view (2010 SP2)

Project Worksheet (PW) and Resource Management Worksheet (RMW) referenced in this article are based on Silverlight technology and are no longer available as of Changepoint 2020

Symptoms:
When running the resource management view not all hours for task assignments are shown for certain resources.

Reason:
Resource does not have any working days in the system; in resource profile all weekdays are marked as non-working days and weekends are already defined as non-working day in the system.



Resolution:
In resource profile, clear out the checkboxes next to weekdays, and save the profile. Demand will appear as expected in resource management worksheet.