Is the cost centre field on the resource profile a reportable field? (2010)

ANSWER:
There is no data provider specifically for resource cost center.

You can create a custom data provider and associate with the resource. For the custom provider you can use Resourceid, Cost center and Resource name (the resource name from Resource table). Then you can link to the out of the box Expense provider (DS_Expense). This out of the box data provider would be the secondary provider.