Warning message when resources are overbooked does not appear in the project planning worksheet (PPW) and project worksheet

For the warning messages to appear in PPW and PW when resources are overbooked, you must configure the following settings in Changepoint Administration:

  1. Enable resource leveling (Resources > Resource Leveling Setup)
  2. On the workgroup for the resource (Resources > Workgroup), select either the option to prevent resources from being overbooked or the option to warn when resources are overbooked.
  3. In Resources > Resource Demand Analysis Setup, configure demand items for entities to be committed.