"Resource" label in task assignment view in Project Worksheet (PPW) is in English only

Symptoms

Regardless of the language setting, the label for the "Resource" field in the task assignment view in Task is displayed in English in the task assignment view in Project Worksheet (PPW). 


Reason

The TaskAssignment.Resource field was not globalized in metadata.

Resolution

Enter the PCID "40389" to the TaskAssignment.Resource field in Metadata:

  1. Access the Metadata view in Changepoint Administration (User Interface > Metadata).
  2. Expand the TaskAssignment folder and then select Resource (Resource).
  3. In the PCID field in the General section, enter 40389.
  4. Click Save