How to assign a resource to the same task for different periods before and after a vacation period?

You cannot assign a resource to the same task with multiple start and finish dates.

Instead, you must assign the resource to the task using the earliest start date and latest finish date. The resource must enter the vacation period in their calendar, and then the vacation period dates will appear as nonworking days in the project planning worksheet, time sheet, resource scheduling worksheet, etc. The duration of the task will be calculated accordingly.