What happens if you change the daily conversion factor for a resource?

You can change the daily conversion factor for a resource by editing the resource profile in User Setup.

Keep the following points in mind:

  • The daily conversion factor is cached, so if you were working with the resource in the project planning worksheet (PPW) or other component, close the window and reopen it.
  • The changed factor applies only to new items (task assignments, time entries, etc.) that are created after the change. The new factor is not automatically applied to items that existed prior to the change, but will be if the item is subsequently updated. For example if you if you edit the planned dates or effort for a task assignment, the daily conversion factor will be applied.