How to allow users to create time entries without having to create task assignments?

Question:
How to allow users to create time entries without having to create task assignments?

Answer:
You will need to set you task as "open task" (checkbox) from the edit task page or the worksheet.
The open task will be visible in the timesheet "open task" section.

Note that the feature "create open task" will be required.