Duration field in MSP do not update planned hours in Changepoint

Question:
In MSP in a linked project, when creating a task with 5 days duration, the planned hours are not updated in Changepoint after saving.
In Changepoint, the Planned hours of the task remains 0 planned hours.


Answer:
Duration in MSP is not updating Planned Hours for Changepoint.
The correct field is "Work" in MSP, equivalent of Planned Hours in Changepoint.