How are the remaining hours calculated?

"Remaining hours" and Percent complete are calculated automatically by Changepoint when the project has the option 'Status Not required' enabled.


Calculation:
Remaining = Planned – Actual (Remaining Hours  equals Planned Hours minus Actual Hours)

If Actual is greater than the Planned Hours, "Remaining Hours" are set to 1.

If the Project has 'Status Required' option enabled, 'Remaining Hours' is updated by the resource or the Project Manager when statusing the task.