How planned hours are calculated for an open task assignment?

QUESTION:
How does Changepoint calculate planned hours for an open task assignment (created when a resource books time to it) ? 


ANSWER:

Planned hours for assignments for open tasks created via the time sheet are inherited from Assignment Planned Hours field on the corresponding task.

Assignment Planned Hours field is disabled and set to 0 if Resource leveling is enabled in the system.