Why are task assignments missing from the resource management worksheet (RMW)?

Project Worksheet (PW) and Resource Management Worksheet (RMW) referenced in this article are based on Silverlight technology and are no longer available as of Changepoint 2020

Completed task assignments are excluded from RMW.

If a task assignment has been completed in error, you can reopen it by updating the status and changing to remaining hours to a number greater than zero.