Overbooked tasks override weekends as working days in Resource Scheduling

When we have two tasks overbooked with red color, and we try to change end date of one task to be before the other one in order to resolve the overbooking, we find the task overriding the weekends as working days.

*ERROR/WARNING MESSAGES:
There are no error messages, but weekends are treated as working days.

*REASON:
The internal (non-)working days tables in Changepoint are not up to date.


*RESOLUTION:
The (non-)working days tables are maintained by the resource demand job. Please make sure that this job is active and running without errors.

After running this job, which is part of the job-chain launched by the job 'Update Time Rate', weekends will correclty be treated as non working days.