Skip to main content
Planview Customer Success Center

Why completed project cannot be filtered on RMW? (CP2012 SP2)

Question:
Using RMW, it is possible to filter on closed requests and navigate to the past periods. Is there any reason this option is not available on projects?


Answer:

The 'Completed' status is filtered out by design due to volumes. As an alternative the Request statuses can be added by customers. The demand volumes are not as large as project, so more flexibility is allowed there.