User is still able to book time to a project despite not having access to the cost structure
Symptoms
User is still able to book time to a project even after removing access to the cost structure.
Reason
A user assigned to a task can log time for the task, regardless of the billing office / cost structure access. This behaviour is by design.
Resolution
If the user should be prevented from booking time to the task,
- the resource assignment needs to be removed from the task.
or
- lock the task assignment
or
- set up time entry restrictions to restrict time entry to be within task/project planned dates