Skip to main content
Planview Customer Success Center

How is slack calculated in Changepoint?

Slack is the amount of time a task can be delayed without affecting the critical path (i.e. without delaying the project).

In Changepoint:

  • Slack is calculated as part of the project critical path calculation
  • Project critical path calculation is only calculated for project with "Calculate critical path" setting enabled.
  • Project critical path calculation is triggered at the end of project rollup process.
  • Draft task and Completed task are excluded in critical path calculation, hence, Slack will have a value of 0.
  • Slack is calculated at each task level based on its PlannedFinish, and it does not get rolled up.
  • Slack is calculated based on task PlannedFinish. Its value is #. of working days between task PlannedFinish and latest task PlannedFinish within the project. And the working days settings are based on project's Engagement's staffing workgroup.
  • Critical path and Slack calculation also take into consideration summary task, task dependency, and sub project hierarchy

Example:

clipboard_e629b5e0fee68e74a2e9905e59452528a.png

In this example, Task 1 and 3 have the same start and finish, but different slack. This is because Task 3 can be delayed up to 9 business days without affecting the overall project duration. Task 1 on the other hand cannot be delayed, as this would also delay Task 2 and thus increase project duration.

As mentioned above, slack doesn't rollup. While Task 3 has a slack of 9, the parent task slack is 0 as delaying it would delay the overall project.