Skip to main content
Planview Customer Success Center

Gaps between Resource Requests (2010)

QUESTION:
Using resource requests and creating a task with manual allocation. When there is effort at the start and at the end of the task but in the middle a few months have 0 effort, is it possible to have two resource requests only, one covering the starting period of the task and one for the end?


ANSWER:
The entire length of the task from planned start to planned finish needs to be covered by resource requests. It is not possible to have a gap in the middle, even if the effort is 0.

Additional notes:
The coverage over the entire length of the task can be done by multiple resource requests, provided there are no gaps in between.