How to enable the "soft booked" checkbox in edit project / project team?

QUESTION

In some projects in the project team section there is a check box 'soft booked' whereas it is missing in others. How is this controlled?


ANSWER

This is a setting at billing office/cost structure level. In order to see the 'soft booked' setting in a project, the corresponding billing office needs the setting 'Allow soft-bookings' to be activated.