QUESTION:
For a project where a certain amount of planned hours can be seen in the project worksheet, a report using the data provider "Financial Analysis by Task Assignment by Monthly" gives a different total.
How can this be explained?


ANSWER:
This can be due to tasks with planned hours but no assignments. These planned hours would increase the total in the project worksheet but would not be taken into account in data providers which are based on task assignments.