Skip to main content
Planview Customer Success Center

If the Fixed Fee item on a Task is updated, when do the Fixed Fee items on the time entries get updated?

Question
If the Fixed Fee item on a Task is updated, when do the Fixed Fee items on the time entries get updated?

 

Answer
The Update Time rate job updates all 'not' invoiced time records with the task latest or new fixed fee.

Invoiced Time records are 'not' or never updated with new fixed fee after fixed fee selection is changed in task.