Start Date and End Date cannot be the same (2012 SP1)
SYMPTOMS:
When creating a request and selecting the same Start Date and End Date in the Resource demand information section, a message is generated:
ERROR/WARNING MESSAGES:
The number of working days between the start and end date is 0, calculated FTEs value will be 0
REASON:
Weekend days were being used
RESOLUTION:
Used weekdays instead.