After copying a project, why do task assignments start later than the task?

When you copy a project and select the option to copy the task assignments (resource assignments), the task assignments are copied as-is to the target project.

That is, the task assignments in the target project will start on the same date relative to the task start date as on the source project. For example, if a task assignment starts three days after the start date of the task on the source project, the task assignment on the target project will start three days after the start date of the task.

You can choose to not copy the task assignments in the Copy Project dialog.