Revenue Recognised Amount is 0 in DS_Project (CP 2012)
QUESTION:
We have recognized and committed revenue for a project, but the amount is not returned in reporting (DS_Project).
ANSWER:
If the revenue is recognized against a fixed fee via PPC, this field in the project data provider DS_Project is 0 as there is no revenue against the project.