How to switch between resource cost rates and billing role cost rates in the budget?

1. Configure the billing office of the parent engagement to use the desired cost rates (that is, switch to resource cost rates from the billing office cost rates):

111111.png

2. To refresh the rates, you must remove the services from the budget, and then add them back by right-clicking and selecting the appropriate Copy from option. 

222222.png