Why did the start and end dates in Resource Demand information change?

On a resource request, the Date Required is the date by which the request must be completed.

On the Resource demand information tab of the resource request, the End Date is the date by which the resource must complete the work for the request.

The End Date must be earlier than the Date Required date. If the End Date is later, then the End Date is changed to the Date Required date, and the Start Date is changed to maintain the initial duration in days from the End Date.

If the Date Required is in the past, then nothing is changed.

Note: The change is performed by the Financial Analysis job Summary (step 3).