Is it possible to configure an irregular work-week? (2014)
QUESTION
One of our departments has an irregular work week:
Monday - Thursday: 8.5 Hours
Friday: 6 Hours
Is it possible to configure this in Changepoint?
ANSWER
This is not possible. It is possible to define resources working more or less than 8 hours per day, but it is not possible to do so based on the day of the week. If a resource is assigned a daily capacity, like 4, 6, 8, 9, .... hours this will be the same value for every working day.