RMW drag and drop of assignment doesn't copy the planned hours correctly (2014)

Project Worksheet (PW) and Resource Management Worksheet (RMW) referenced in this article are based on Silverlight technology and are no longer available as of Changepoint 2020

SYMPTOMS

Task assignments are reassigned in the RMW using drag and drop. Sometimes it happens that the effort from the source assignment is not correctly transferred to the destination task.

It seems like effort is missing in some fiscal periods in the destination assignment and it is moved into the next fiscal period.

 

RESOLUTION

This can happen when there are additional non-working days for the destination resource. In that case, the effort is moved to the next day and it also means that some effort might be shifted into the next fiscal period.

This is not a defect but the intended behavior to avoid planning effort on non-working days.