Why a task assignment does not appear in resource's calendar?
The task assignment needs the "Add to Calendar" option selected and the project must be in Active status for task assignments to appear in resource's calendars.
The task assignment needs the "Add to Calendar" option selected and the project must be in Active status for task assignments to appear in resource's calendars.