Late tasks report in 'My Reminders' portlet shows task with future planned finish date
QUESTION
The report 'Late Tasks' which is opened from the 'My Reminders' portlet shows tasks with a future planned finish date. Shouldn't it only show tasks with a past date?
ANSWER
This report lists tasks where the forecast end date for the logged in user is in the past. This can be different from the planned finish date for the task which is displayed in the report.
To see the more data for a task in that report, click on the task name to see the detail about planned and forecast finish dates for all assigned resources.